Read a calculation result
Check placement, capacity and unplaced work before adopting the plan.
Review in this order
- Check the selected team, horizon and input data.
- Use Timeline to inspect task order, dates and dependencies. Open a task to see its activities and assigned people.
- Review unplaced work and the stated reasons instead of assuming that missing work was completed.
- Check occupied and remaining capacity in the summary. These are planned quantities, not actual hours worked.
Read intervals carefully
A task’s first and last dates do not mean uninterrupted work between them. Meetings, non-working time, dependencies and other constraints can create gaps. Work shown after the planning horizon is a forecast with different constraints; read the explanation shown with the result. A calculation is a recommendation, not automatic approval of a plan.
Related articles
- Understand task priority
Read priority together with dependencies, estimates and available capacity.
- Repeat a calculation after changes
Refresh the inputs, review changes and preserve the previous result.