Field mapping and estimate units

Distinguish an original estimate, time spent and remaining work.

Map the meaning, not just the name

Match each relevant source field to the correct planning parameter. An original estimate, time spent and remaining work describe different quantities. Check examples from your file before confirming a match. New people or statuses may require reference-data updates even when the column structure stays the same.

Confirm units

Specify the unit for each effort field. If estimates use story points or another non-time unit, provide the conversion to working time. Do not assume that remaining work uses the same unit as the original estimate. For example, 6 hours estimated, 2 hours spent and 240 minutes remaining describe 4 hours of remaining main work.