Review task data before calculating
Resolve missing work estimates and external deadlines; review other warnings.
What needs correction
Included work needs a positive estimate for the work still to be scheduled. An included external dependency needs a deadline. Completed activities are not planned again. If a task has no work left, do not invent an estimate merely to pass validation; check its status and inclusion.
Time spent without a start date
If work has already started, enter its actual start date when you know it. A missing start date does not block calculation, but the priority calculation is simplified. The service does not infer a start date by subtracting spent hours from a date.
Check changes before starting
Save task edits and confirm that warnings are resolved or understood. Excluding a task changes the calculation scope; it is a planning decision, not a substitute for correcting the source.
Related articles
- Field mapping and estimate units
Distinguish an original estimate, time spent and remaining work.
- Task hierarchy and dependencies
Separate parent-child structure from work that blocks other work.